Mahoning Valley Development Tracker
A free, current list of capital projects and data center rules being followed across the Valley, drawn from public records and Cornerstone research. Issue 38, dated Monday, Nov. 23, 2026.
Capital pipeline
This week we recorded 6 changes across 65 projects being followed, including 1 new project.
WHAT MOVED THIS WEEK
- Wick Lofts, Youngstown New
YNDC and Pivotal Housing Partners' 63-unit plan is now listed at $20 million, with an April groundbreaking and about 15 months of construction. The land sale and permits are pending. Issue 37 had $19 million and a spring 2027 start. - Youngstown Wet Weather Facility
Council held the 14% annual sewer increases and about $100 million in Phase 2 and 3 legislation in committee. The Phase 1 award was pulled from the Nov. 19 Board of Control. The project's stage is unchanged. - Vallourec premium threading line
The $48 million line on Martin Luther King Jr. Boulevard has been commissioned and is running. Third-quarter EBITDA was $181 million, down 26%. - Sharon Regional
The state closure order took effect Nov. 17. The Herald reported Nov. 19 that a Nov. 20 final payday was expected to be missed. No source has confirmed whether that payroll was paid. - SOBE Thermal
The receiver said the plant failed to pay $37,404.94 in property taxes and that cash runs out in late January or early February without government help. - McDonald Steel site
Oppidan issued a community FAQ on a scaled-back five-building campus. Residents asked for a ballot ban; the solicitor said the village cannot place it. The one-year moratorium stands.
Data center register
The data center register covers 36 jurisdictions, with 10 updates this week. No jurisdictions were added.
WHAT MOVED THIS WEEK
- Youngstown
Valor closed its Logan Avenue purchase. Council members have discussed a moratorium; no legislation has been introduced, and the mayor said no applications have been filed. - Champion Township
Trustees unanimously enacted a three-month data center moratorium. - Howland Township
Trustees extended the moratorium for another six months. The prior term was scheduled to expire Dec. 10. - Bazetta Township
Res. 156-26, a 180-day extension from Nov. 13, passed Nov. 10. A zoning workshop is set for Nov. 24. - Perry Township (Lawrence)
Ordinance 11-12-26 was enacted Nov. 12 and is effective immediately. - McDonald Village
Oppidan issued a FAQ; residents asked for a ballot ban the solicitor said the village cannot place. The one-year moratorium stands. - New Beaver Borough
The Nov. 18 hearing was held. A special meeting is set for Nov. 23 at 7 p.m. - North Beaver Township
Review of the Stonebridge land development plan was tolled to Nov. 29. - Neshannock Township
The proposed ordinance was on the Nov. 16 and Nov. 18 agendas; the outcome is UNCONFIRMED. A Dec. 2 hearing is on a separate rezoning. - Sharon
Second reading of a replacement zoning ordinance was on the Nov. 18 agenda; the vote is UNCONFIRMED.